Update on Garretson Street project from Sayre Associates, Inc.

Date:

Main Ave Construction

The project consists of reconstruction of the street and utilities on Third Street from Depot Avenue to Oak Avenue, Main Avenue from Second Street to Fifth Street, Railroad Avenue from Dows Street to Essex Street, Essex Street from Railroad Avenue to Granite Avenue and Granite Avenue from Essex Street to First Street. Portions of this project were previously constructed in 2018 and 2019.

Project Information

First Rate Excavate has removed asphalt to the north side of Steve’s Electric on Main Avenue and to the east side of First Bank and Trust along 4th Street. The temporary water services have been connected for those affected by the utility improvements. They have replaced the existing clay sewer with a new PVC sewer main from 4th Street to Steve’s Electric. First Rate has also installed new storm sewer across Main Avenue and have begun watermain installation going north from 3rd Street.

Next, First Rate will install a sanitary sewer main east of Main Avenue along 4th Street. The installation and reconnecting of sanitary sewer services will also be taking place. They will continue to install the watermain along both Main Avenue and 4th Street as well. Finally, once the bacteria test has passed, First Rate will begin reconnecting the water services.

Main Ave construction

Sayre Associates, Inc. is providing the construction administration and on-site observation for the project. If you have any questions or concerns regarding this project, please contact Cole Gebhart or Doug Hoy. Their contact information is to the left.

Construction bulletins will detail the progress of the project as it is constructed and is distributed every two weeks on Monday. To be placed on the email distribution list, call Carrie at (605) 332-7211 or email .

Original Bid Price: $3,383,601.18

New Completion Date: November 15, 2020

Sayre Associates is a private engineering firm hired by the City of Garretson to provide construction updates and administration for this project. Please contact the project team members below with any questions or concerns.

Sayre Associates Project Engineers
Cole Gebhart Cell: (605) 321-3868; Office: (605) 332-7211 or Doug Hoy Cell: (605) 940-1055;
Office: (605) 332-7211

City of Garretson Utilities Superintendent Craig Nussbaum Phone: (605) 594-6723

First Rate Excavate, Inc. Contractor
Jason Snyders Cell: (605) 351-2561
Office: (605) 331-5626

Share post:

spot_img

Related articles

Judge dismisses lawsuit from neighbors opposed to men’s prison site

State law trumps county ordinances, Lincoln County judge rules By: John Hult, SD Searchlight             A Lincoln County judge has dismissed...

Interstate 90 Lane Closures and Traffic Diversions Planned at Brandon

BRANDON, S.D. – Beginning at 7 p.m. on Tuesday Aug. 27, 2024, the South Dakota Department of Transportation...

4th Street project started this past Monday, here is what you need to know

Carrie Moritz, Gazette             Last week Tuesday, an open house-style public meeting was held regarding the 4th Street Project....

Eastbound Off-Ramp Closure Planned at Exit 406 (Brandon) for Utility Work

BRANDON, S.D. – Beginning Tuesday, May 7, 2024, the Interstate 90 eastbound off-ramp at exit 406 (Brandon) will...

Log In

Latest articles

G-Town Hair-We-Go opens this week

Garrick A. Moritz, Gazette Kimberly Ann Anderson first moved to Garretson back in 2020. “I liked the community right away,...

School adopts E-learning plan for snow days

By Carrie Moritz,  Garretson Gazette Despite a drier winter so far, Garretson School District students will join other districts in...

Natural Gas prices remain high, new speed limits

By Carrie Moritz,  Garretson Gazette A new business will be built in the industrial development, speed limits on Dows Street...

Garretson Area in 2024 Year in Review, part 2

The second half of 2024 was no less eventful than the first half had been, and saw the...

Garretson Library renovation celebration

The Siouxland Libraries- Garretson Branch held an open house this past Saturday to celebrate the conclusion of its...

Exercise Place update, a bunch of brand new gear

The Exercise Place is well on the way to helping Garretson accomplish its fitness goals, thanks to the...
s2Member®