Fourth Street Update:

Date:

road torn open showing sewer replacement
//photo courtesy Sayre Associates

            First Rate has installed all the sanitary sewer main between Canyon Ave and Eastern Ave. A number of sewer services on this stretch of roadway have also been replaced.

            In addition, all residents along Fourth Street have been connected to the temporary water main.

            Next, First Rate will finish installing the sanitary sewer main and services within Phase 1.

            The Phase 1 project limits are 200 feet east of Eastern Avenue. Once all the sewer services are installed, First Rate will begin installing water main between Main Avenue and Eastern Avenue.

            Lastly, Xcel Energy will be relocating the power poles along Eastern Avenue. Their relocation is necessary for future curb and gutter and sidewalk installs.

            Sayre Associates is providing construction administration and on-site observation for the project. If you have any questions or concerns regarding this project, please contact Cole at (605) 321-3868 or .

            Construction bulletins will detail the progress of the project as it is constructed and will be distributed every two weeks on Tuesday. To be placed on the email distribution list, please contact Carrie at (605) 332-7211 or .

Share post:

spot_img

Related articles

Traffic Modifications Planned on Reconstruction Project (Exit 406) at Brandon

BRANDON, S.D. – On Friday, Nov. 1, 2024, traffic on S.D. Highway 11 will be switched from the existing...

4th Street update from First Rate Construction

            First Rate finished installing the sanitary sewer main and water main within Fourth Street. The water main...

Fourth Street Update

-submitted by Sayre Associates, Inc.             First Rate Excavate has removed the asphalt and concrete surfacing along Fourth Street...

4th Street project started this past Monday, here is what you need to know

Carrie Moritz, Gazette             Last week Tuesday, an open house-style public meeting was held regarding the 4th Street Project....

Log In

News for 11-21-24

Latest articles

News for 11-21-24

The first phase of 4th Street is nearly completed, as the asphalt company began laying their product this...

North Dakota approves Summit carbon pipeline route

Company reapplied this week in South Dakota By: Jeff Beach, North Dakota Monitor North Dakota regulators on Friday approved a route...

Presidential pause in relocations

How the 2024 election impacts business and family moves. “This is about the stupidest year I’ve seen." By Megan...

News for 11-21-2024 (e-edition)

This Week's Issue Download this week's issue Community Events Calendar The first phase of 4th Street is nearly completed, as the...

Pierret Benefit this Saturday

This Saturday, head to Mike's Bar in Sherman to help support the Mark Pierret Benefit! Mark was in...

Ambulance crew to set new records

By Carrie Moritz, Gazette Garretson Ambulance Supervisor Kurtis Nelson spoke to the Garretson City Council last week Monday about...
s2Member®