First Rate has installed all the sanitary sewer main between Canyon Ave and Eastern Ave. A number of sewer services on this stretch of roadway have also been replaced.
In addition, all residents along Fourth Street have been connected to the temporary water main.
Next, First Rate will finish installing the sanitary sewer main and services within Phase 1.
The Phase 1 project limits are 200 feet east of Eastern Avenue. Once all the sewer services are installed, First Rate will begin installing water main between Main Avenue and Eastern Avenue.
Lastly, Xcel Energy will be relocating the power poles along Eastern Avenue. Their relocation is necessary for future curb and gutter and sidewalk installs.
Sayre Associates is providing construction administration and on-site observation for the project. If you have any questions or concerns regarding this project, please contact Cole at (605) 321-3868 or
Construction bulletins will detail the progress of the project as it is constructed and will be distributed every two weeks on Tuesday. To be placed on the email distribution list, please contact Carrie at (605) 332-7211 or