CHIP SEAL AND FOG SEAL PROJECTS SCHEDULED FOR SIOUX FALLS AREA

Date:

SIOUX FALLS, S.D. – The South Dakota Department of Transportation (SDDOT) says chip seal and fog seal applications will be applied to several highways in the Sioux Falls area of the state. The chip seal will begin on Monday, July 25, 2022.

Weather dependent, the contractor will move from one project to the next in the following scheduled order:

  1. S.D. Highway 115 – Project runs for nine miles from U.S. Highway 18 to Lincoln County Road #110. The approximate time to complete the chip seal on this route is two days. 
  2. S.D. Highway 11 – Project runs for one half mile through the turn lanes at the 273rd Street intersection. The approximate time to complete the chip seal on this route is one day.  
  3. S.D. Highway 11– Project runs for 21 miles from Corson to the MN|SD state line. The approximate time to complete the chip seal on this route is five days.
  4. S.D. Highway 34  - Project runs for one mile through the turn lanes at the intersections of 463rd Avenue and 464th Avenue. The approximate time to complete the chip seal on this route is one day. 

A fog seal application will follow the chip seal operation on each route within a few days.

Traffic will be reduced to one lane and guided through the project with the use of flaggers and a pilot car. A delay of up to 15 minutes can be expected while traveling through the work area during daytime hours.

Loose gravel will be present for a period of 36 to 72 hours after each day’s chip seal application. Traffic should travel at 40 mph, or the posted speed limit if it is less than 40 mph, during this time frame.

The permanent pavement marking is scheduled to be applied within 14 days of completion of the chip and fog seal projects. 

The Road Guy Construction Company of Yankton, SD, is the prime contractor on the $1 million project.

About SDDOT:

The mission of the South Dakota Department of Transportation is to efficiently provide a safe and effective public transportation system.

For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit https://sd511.org or dial 511.

Read more about the innovative work of the SDDOT at https://dot.sd.gov.

Share post:

spot_img

Related articles

Judge dismisses lawsuit from neighbors opposed to men’s prison site

State law trumps county ordinances, Lincoln County judge rules By: John Hult, SD Searchlight             A Lincoln County judge has dismissed...

Interstate 90 Lane Closures and Traffic Diversions Planned at Brandon

BRANDON, S.D. – Beginning at 7 p.m. on Tuesday Aug. 27, 2024, the South Dakota Department of Transportation...

4th Street project started this past Monday, here is what you need to know

Carrie Moritz, Gazette             Last week Tuesday, an open house-style public meeting was held regarding the 4th Street Project....

Eastbound Off-Ramp Closure Planned at Exit 406 (Brandon) for Utility Work

BRANDON, S.D. – Beginning Tuesday, May 7, 2024, the Interstate 90 eastbound off-ramp at exit 406 (Brandon) will...

Log In

Latest articles

Phase One of 4th street project nears completion

Concrete crews have completed all concrete work on 4th Street, Center Avenue and Canyon Avenue including curb and...

Williamson proud of his service & grateful for the Honor Flight

By Garrick Moritz, Gazette Mark Williamson was pretty humble about his recent trip to Washington DC on an Honor...

Jasper man dies in fatal crash

Minnehaha County, S.D.- A Jasper, MN man died in a collision Thursday evening, November 14, three miles north...

Pierret Benefit Well Supported

Though we have not received the final tally of funds raised at the Mark Pierret Benefit held on...

GHS Football celebrates players

The GHS Annual Football Banquet honored the parents and players after a rough season on Monday, Nov. 18. The...

A new sport at Garretson

The rise of powerlifting across the state has found its way back to the Blue Dragons by Delilah Johnson,...
s2Member®