4th Street update from First Rate Construction

Date:

            First Rate finished installing the sanitary sewer main and water main within Fourth Street. The water main has been pressure and bacteria tested as well. All sewer services are complete and nearly all water services have been installed.

construction workers looking at a large rectangular hole with pipe on the bottom
First Rate worked to install the new sanitary sewer line along 4th Street. //photo courtesy Sayre Associates

            First Rate had also removed the asphalt and concrete surfacing on Center and Canyon Avenues between Third and Fourth Streets.

            Now, First Rate finished installing the water services within Fourth Street. They also installed all sanitary sewer and water main on Center and Canyon Avenue between Third and Fourth Street. Base course has been placed along Fourth Street between Main Avenue and Eastern Avenue as well.

            Next, First Rate will finish installing water services and storm sewer on Center and Canyon Ave. Once finished, the roadways will be graded in preparation for base course. The concrete subcontractor will be installing curb and gutter, fillets, valley gutters, sidewalk and approaches along Fourth Street.

pipeline side by side with one on left showing deteriorating condition and one on right in brand new condition
A comparison between the old storm sewer pipe (left photo) and the new storm sewer main (right photo) shows the deterioration of the old system. //photos courtesy Sayre Associates

            Sayre Associates is providing on-site construction administration and observation for the project. If you have any questions or concerns regarding this project, please contact Cole at (605) 321-3868 or . Construction bulletins will detail the progress of the project as it is constructed. To be placed on the email distribution list, please contact Carrie at (605) 332-7211 or .

Share post:

spot_img

Related articles

Phase One of 4th street project nears completion

Concrete crews have completed all concrete work on 4th Street, Center Avenue and Canyon Avenue including curb and...

Traffic Modifications Planned on Reconstruction Project (Exit 406) at Brandon

BRANDON, S.D. – On Friday, Nov. 1, 2024, traffic on S.D. Highway 11 will be switched from the existing...

Fourth Street Update:

            First Rate has installed all the sanitary sewer main between Canyon Ave and Eastern Ave. A number...

Fourth Street Update

-submitted by Sayre Associates, Inc.             First Rate Excavate has removed the asphalt and concrete surfacing along Fourth Street...

Log In

Latest articles

SDPB to Host Dakota Life Screening in Garretson 2/5

Join SDPB for a free screening of Dakota Life Greetings from Garretson on Wednesday, February 5th, at Garretson American Legion, 504 N...

Paulson and Farm 484 finalist for 2024 S.D. Specialty Crop Producer of the Year

Dan Paulson of Farm 484 in Sherman, SD is a finalist in The South Dakota Specialty Producers Association...

Garretson 4th graders special project, research and write on the Winter Olympics

Carrie Moritz, Gazette Garretson Elementary fourth graders have had a busy January so far, researching and writing about Winter...

Annie’s announces move to Brandon

Last week, the Brandon Development Foundation and Brandon Valley Journal announced that Annie's Coffee Bar would be moving...

Hundreds crowd public hearing on second attempt at a carbon pipeline permit

Comments focus on economic development vs. safety, property rights By Makenzie Huber, South Dakota Searchlight SIOUX FALLS — Hundreds of people,...

GHS One Act Play Sunday!

The Garretson High School One Act Play season has been in full swing throughout January, with a full...
s2Member®