4th Street update from First Rate Construction

Date:

            First Rate finished installing the sanitary sewer main and water main within Fourth Street. The water main has been pressure and bacteria tested as well. All sewer services are complete and nearly all water services have been installed.

construction workers looking at a large rectangular hole with pipe on the bottom
First Rate worked to install the new sanitary sewer line along 4th Street. //photo courtesy Sayre Associates

            First Rate had also removed the asphalt and concrete surfacing on Center and Canyon Avenues between Third and Fourth Streets.

            Now, First Rate finished installing the water services within Fourth Street. They also installed all sanitary sewer and water main on Center and Canyon Avenue between Third and Fourth Street. Base course has been placed along Fourth Street between Main Avenue and Eastern Avenue as well.

            Next, First Rate will finish installing water services and storm sewer on Center and Canyon Ave. Once finished, the roadways will be graded in preparation for base course. The concrete subcontractor will be installing curb and gutter, fillets, valley gutters, sidewalk and approaches along Fourth Street.

pipeline side by side with one on left showing deteriorating condition and one on right in brand new condition
A comparison between the old storm sewer pipe (left photo) and the new storm sewer main (right photo) shows the deterioration of the old system. //photos courtesy Sayre Associates

            Sayre Associates is providing on-site construction administration and observation for the project. If you have any questions or concerns regarding this project, please contact Cole at (605) 321-3868 or . Construction bulletins will detail the progress of the project as it is constructed. To be placed on the email distribution list, please contact Carrie at (605) 332-7211 or .

Share post:

spot_img

Related articles

Garretson Area Briefs

Adults Night Out, Ambulance Breakfast, Splitrock Bowling, I-90/Brandon Interchange Construction Adult Night Out The Garretson PTO will be hosting Adults...

4th Street Construction to resume March 31st

First Rate Excavate plans to begin removals on Phase 2 starting on Monday, March 31st, weather permitting. This...

I-90 and Brandon interchange construction to re-start

On Monday March 24, 2025, lane closures will be placed on westbound Interstate 90 at Brandon (exit 406)...

Phase One of 4th street project nears completion

Concrete crews have completed all concrete work on 4th Street, Center Avenue and Canyon Avenue including curb and...

Log In

Latest articles

Election, new playground, new statue

The Garretson School Board met in regular session on April 14, 2025. Main topics of discussion were the...

A deep dive on ordinances for the City of Garretson

By Carrie Moritz, Gazette Garretson City Councilor Brayden Beaner has been working through the City of Garretson's code book...

Local election recap and summary

Though voter turnout was relatively low (it was not as low as it has been in some previous...

COUNCILOR UPDATE

By City Councilor Brayden Beaner This will be the first of what I hope will become monthly updates on...

A windy Jesse James Track meet

The first outdoor meet of the Garretson Track & Field season was held last Saturday on the home...

4 more Games, 2W 2L for Blue Dragon Baseball

Two games on the home field produced two wins for the Garretson Blue Dragon baseball team this past...
s2Member®