4th Street construction begins Monday

Date:

            On Tuesday, an open house-style public meeting was held regarding the 4th Street Project. There, attendees learned the contractor intended to start Monday, July 29 with equipment move-in and mobilization and Tuesday, July 30 with the full project.

            This will mean 4th Street will be closed from Main Avenue to Eastern Avenue until mid-to-late November, when Phase I is expected to wrap up. Side streets between 3rd and 4th will be closed for the same project. These include Center Avenue, Canyon Avenue, and Eastern Avenue.

            The street closure will bring updated infrastructure to the area, which includes a larger water main (from 4" to 6" in many areas), sanitary sewer line, storm sewer, curb and gutter, new pavement, and sidewalks.

            While many attendees were concerned for their mature trees, not all will need to be removed as the contractor is planning to work around many of them. Those trees affected are those that have water or sewer lines under them, or are placed too close to the right-of-way.

            The contractor and engineers from First Rate Excavate and Sayre Associates assured everyone that any specific requests will be taken under consideration, and all efforts would be made to ensure everyone had access to their homes. However, no traffic will be allowed on the street between Main and Eastern during the project.

            Phase II will begin next April, weather permitting. That will include the area between Eastern and Oak Drive.

            More information will be available in next week's edition of the Gazette.

Share post:

spot_img

Related articles

Traffic Modifications Planned on Reconstruction Project (Exit 406) at Brandon

BRANDON, S.D. – On Friday, Nov. 1, 2024, traffic on S.D. Highway 11 will be switched from the existing...

4th Street update from First Rate Construction

            First Rate finished installing the sanitary sewer main and water main within Fourth Street. The water main...

Fourth Street Update:

            First Rate has installed all the sanitary sewer main between Canyon Ave and Eastern Ave. A number...

Fourth Street Update

-submitted by Sayre Associates, Inc.             First Rate Excavate has removed the asphalt and concrete surfacing along Fourth Street...

Log In

News for 11-21-24

Latest articles

News for 11-21-24

The first phase of 4th Street is nearly completed, as the asphalt company began laying their product this...

North Dakota approves Summit carbon pipeline route

Company reapplied this week in South Dakota By: Jeff Beach, North Dakota Monitor North Dakota regulators on Friday approved a route...

Presidential pause in relocations

How the 2024 election impacts business and family moves. “This is about the stupidest year I’ve seen." By Megan...

News for 11-21-2024 (e-edition)

This Week's Issue Download this week's issue Community Events Calendar The first phase of 4th Street is nearly completed, as the...

Pierret Benefit this Saturday

This Saturday, head to Mike's Bar in Sherman to help support the Mark Pierret Benefit! Mark was in...

Ambulance crew to set new records

By Carrie Moritz, Gazette Garretson Ambulance Supervisor Kurtis Nelson spoke to the Garretson City Council last week Monday about...
s2Member®