4th Street construction begins Monday

Date:

            On Tuesday, an open house-style public meeting was held regarding the 4th Street Project. There, attendees learned the contractor intended to start Monday, July 29 with equipment move-in and mobilization and Tuesday, July 30 with the full project.

            This will mean 4th Street will be closed from Main Avenue to Eastern Avenue until mid-to-late November, when Phase I is expected to wrap up. Side streets between 3rd and 4th will be closed for the same project. These include Center Avenue, Canyon Avenue, and Eastern Avenue.

            The street closure will bring updated infrastructure to the area, which includes a larger water main (from 4" to 6" in many areas), sanitary sewer line, storm sewer, curb and gutter, new pavement, and sidewalks.

            While many attendees were concerned for their mature trees, not all will need to be removed as the contractor is planning to work around many of them. Those trees affected are those that have water or sewer lines under them, or are placed too close to the right-of-way.

            The contractor and engineers from First Rate Excavate and Sayre Associates assured everyone that any specific requests will be taken under consideration, and all efforts would be made to ensure everyone had access to their homes. However, no traffic will be allowed on the street between Main and Eastern during the project.

            Phase II will begin next April, weather permitting. That will include the area between Eastern and Oak Drive.

            More information will be available in next week's edition of the Gazette.

Share post:

spot_img

Related articles

Phase One of 4th street project nears completion

Concrete crews have completed all concrete work on 4th Street, Center Avenue and Canyon Avenue including curb and...

Traffic Modifications Planned on Reconstruction Project (Exit 406) at Brandon

BRANDON, S.D. – On Friday, Nov. 1, 2024, traffic on S.D. Highway 11 will be switched from the existing...

4th Street update from First Rate Construction

            First Rate finished installing the sanitary sewer main and water main within Fourth Street. The water main...

Fourth Street Update:

            First Rate has installed all the sanitary sewer main between Canyon Ave and Eastern Ave. A number...

Log In

Latest articles

Hometown Christmas fun

Saturday's Hometown Christmas was a success despite some less-than-ideal weather. The Legion was packed with holiday cheer as...

2024 Christmas Holiday Drawing Contest winners!

A word to our sponsors! Thank you to Alliance Communications, Blue Dragon Academy, CHS, the City of Garretson, Don’s...

Intercepted Santa Letters!

A little elf at the Garretson Elementary School was able to sneak away some "Dear Santa" letters from...

Amanda Schotzko explores her Korean heritage

By Carrie Moritz, Gazette As far as Amanda Schotzko knew, she was given up for adoption because her birth...

GHS Boys Varsity Basketball begins with 1 win, 1 loss

The Garretson Varsity Boys Basketball team shot out of the gate last week with two back-to-back games on...

GHS Girls Bball vs Tri-Valley & Chester

The Garretson Girls Varsity Basketball team has had a rough start to the season, with Tri-Valley and Chester...
s2Member®